Posts by thomas

President’s Report February 2021

Now THAT was a snowstorm. I hope everyone got through it ok. The Water Company’s generators insured that water was deliverable and we were able to keep our office emergency lines open (intermittently) to serve any customer needs. I have a couple of words for the month: #1 WINTERIZING Winterizing is a fancy word for…

General Manager’s Report February 2021

Dear Shareholders, The week of January 24th brought a major storm to our area. The storm caused widespread damage to Arnold and Blue Lake Springs, with power outages lasting several days. Your water company was working hard to keep the water flowing. Using our portable emergency generator, we were able to pump water from Tank…

President’s Report January 2021

First and foremost: Happy New Year!! 2021 will be a better year, if we give it a chance. If you are wondering where are Mozingo’s heavy trucks and construction equipment, they left in late December. The 12.2M dollar system improvement project is complete and, in a few days the remaining paperwork will be signed with…

General Manager’s Report January 2021

Dear Shareholders, 2020 was a year none of us have experienced before, and I am looking forward to things getting back to normal in the next few months. Our office is closed to the public but we are here and working. Just knock on the door and we will take care of you. USAGE Water…

President’s Report December 2020

Over the past few months, I have indicated that the Project is coming to a close. Now all is finally complete. Mozingo has packed up their equipment and moved onto another job site. As the Project’s Contractor, they did an incredible job, and the Water Company is very pleased with their performance and delivery of…

General Manager’s Report December 2020

The year is almost over, and what a year it was. Our Infrastructure Improvement project is complete, and we should close out by the first week in January. The weather is nice, so if you haven’t connected to your new service box, now is the time. Call the office if you have any questions on…

LRPC December 2020

Over the past couple months the primary focus has been on-going close coordination with MC Engineering on managing the USDA Project completion and closeout as effectively as possible to reduce further schedule delays and/or cost impacts. Based on weather delays, construction manpower issues and multiple attempts to get the new pump station working properly, the…

LRPC October 2020

Over the past couple months, LRPC efforts have focused on the remaining USDA Project scope and continuing the development of Asset Management Plan funding options. The LRPC has been working with MC Engineering to complete fact-finding and negotiation of their proposed Amendment 7. Based on construction weather delays from this past winter and previous new…

General Manager’s Report October 2020

Dear Shareholders, Fall is here and it’s time to check your irrigation systems. Look for any leaks, broken sprinkler/mister heads, and bad timers. Also start thinking about winterizing your irrigation and cabin. It’s still quite warm out for October, but this can change fast as the days go by. USDA Infrastructure Project The last piece…

President’s Report October 2020

Included in the past few Bubblers, I have alluded to the impending conclusion of the infrastructure project. That moment is now before us. Final touches and “punch-list” work are starting to be addressed which are signs that the project is truly coming to a close. There a lot of folks to thank: Dave Hicks, the…